MUFFLE FURNACE

SOP FOR CLEANING, CALIBRATION AND OPERATION

1.0 OBJECTIVE

To check the instrument performs satisfactorily and gives accurate temperature.

2.0 SCOPE

This SOP Covers the operation and calibration procedure of Muffle furnace and this SOP is applicable to Quality Control Department.

3.0 RESPONSIBILITY

Officer / Executive

4.0 ACCOUNTABILITY

Department Head.

Muffle Furnace

5.0 PROCEDURE

5.1 CLEANING PROCEDURE

5.1.1 Check that the power supply to the instrument is switched “OFF”.

5.1.2 Ensure that the Muffle Furnace is not in hot condition or in operation while cleaning.

5.1.3 Clean the instrument externally with clean dry cloth.

5.2 OPERATING PROCEDURE

5.2.1 Ensure that the instrument is connected to the power supply.

5.2.2 Switch “ON” the main power supply, glowing of red light at mains indicates the power supply.

5.2.3 Switch on the instrument by ON position which leads to activation of green control bulb and the temperature controller.

5.2.4 Set the temperature required by pressing and holding the red ‘PRESS TO SET’ button and rotate the adjust screw to set the required temperature and release the push button.

5.2.5 The digital display shows the actual temperature of furnace and the red light of the temperature controller glows.

5.2.6 When temperature reaches at the setting point, the red light of temperature controller automatically switched “OFF” and green light will glow. The equipment is now ready for operation.

5.2.7 If any discrepancy observed during operation, inform to maintenance department for rectification.

5.3 CALIBRATION PROCEDURE

5.3.1 Calibration of the temperature will be done through external agency from Calibration Service laboratory.

5.3.2 If any discrepancy observed during operation, stop the instrument and inform to Utility department for rectification and affix “BREAK-DOWN” tag to the instrument .

5.3.3 FREQUENCY OF CALIBRATION
Once a year and after each Maintenance Job.


6.0 REASON FOR REVIEW
First time issue.

Previous Page Next Page

People Searching On This Page:
  • Www.calibration of muffle furance.com
  • muffle furnace procedure
  • sop for calibration of muffle furnace
  • muffle fuenace operating producer
  • muffle furnace operating procedure
  • muffal furnace temp calibratin
  • muffle furnace working procedure
  • calibrtion of muffle furnace
  • calibration of muffle furbace
  • calibration of muffle furnace
  • sop for muffle furnace
  • operational qualification for muffle furnace
  • usp furnace
  • usp method 231 method II muffle furnace
  • muffle furnace operating method

Related Pages


Vernier Calliper’s - Operation & Calibration

Vernier Calliper’s - Operation & Calibration

Articles | Pharmaceutical Equipment
Date:
09-Oct-2011  Views: 5888

To lay down procedure to operate and calibrate Digimatic Vernier Calliper. ...
Laminar Air Flow - Operation & Calibration

Laminar Air Flow - Operation & Calibration

Articles | Pharmaceutical Equipment
Date:
03-Oct-2011  Views: 13504

To lay down a Standard Operating Procedure for laminar flow. ...
Brookfield Viscometer - Operation & Calibration

Brookfield Viscometer - Operation & Calibration

Articles | Pharmaceutical Equipment
Date:
23-Sep-2011  Views: 6592

To provide a procedure for the operating Brookfield viscometer. ...
Disintegration Tester - Operation & Calibration

Disintegration Tester - Operation & Calibration

Articles | Pharmaceutical Equipment | Tablet
Date:
01-Sep-2011  Views: 10341

Tablet disintegration testing is used as a quality-assurance measure. It is not a true predicter of how well the dosage form will release its active i ...
Centrifuge - Calibration and Operation

Centrifuge - Calibration and Operation

Articles | Pharmaceutical Equipment
Date:
30-Aug-2011  Views: 3871

To lay down an operating procedure and calibration of Centrifuge apparatus. ...
Post Your Comments (No Login Require)
Name : (required)
Email : (required)
Website :

Comment : (required)

8  + 3 =     
Comments
People Searched About:
Www.Calibration Of Muffle Furance.Com   |   Muffle Furnace Procedure   |   Sop For Calibration Of Muffle Furnace   |   Muffle Fuenace Operating Producer   |   Muffle Furnace Operating Procedure   |   Muffal Furnace Temp Calibratin   |   Muffle Furnace Working Procedure   |   Operational Qualification For Muffle Furnace   |   Usp Furnace   |   Usp Method 231 Method II Muffle Furnace   |   Muffle Furnace Operating Method   |   Furnace Calibration SOP   |   Muffle Furnaces   |   SOP On Furnace Operation   |   Muffle Furnace 48000 Temperature Calibration   |   Calibration Of Mufle Furnace   |   SOP Muffle Furnace   |   Furnance Calibration   |   Calibration Of Furnace Method BY Usp   |   Operation Procedure Of Muffle Furnace   |   Furnace Temperature Calibration Method   |  
Google : 1094 times | Yahoo : 48 times | Bing : 452 times |